ISI SEZ was officially launched on 10 January 2025, marking the commencement of its development as a fully integrated and sustainable industrial township. The launch signifies the project’s transition from planning to execution, with construction development now actively underway.
About ISI SEZ
Project development is progressing in an orderly and controlled manner. Factories, infrastructure, clean water treatment plant and wastewater treatment plant, substation are advancing in parallel, translating the master plan into tangible result.
OFFICE COMPLEX
READY-BUILT FACTORY
WASTEWATER TREATMENT PLANT
WORKER DORMITORY
FACTORY CONSTRUCTION PROGRESS
ONE–STOP SERVICE & OFFICE COMPLEX
The construction of one-stop service and office complex is progressing steadily with approximately 99% completion, as the structure begins to take shape and key elements of the complex come together.
READY-BUILT FACTORY
Construction of the Ready-Built Factory has completed. The project is progressing steadily toward delivering high-quality, move-in-ready industrial space to support early tenant occupancy and leasing opportunities.
CLEAN WATER TREATMENT PLANT
The Clean Water Treatment Plant is completed to ensure a stable and compliant clean water supply for ISI SEZ. Civil works and system installations are progressing in line with the approved construction schedule, supporting long-term operational reliability across the zone.
WASTEWATER TREATMENT PLANT
The Wastewater Treatment Plant has completed. It has been developed to meet environmental and regulatory standards, enabling effective wastewater management for industrial users within the SEZ. Construction is advancing in phases, with key structural and technical works underway to support compliant and sustainable operations.
INFRASTRUCTURE
Construction of the Zone Internal Main Road has been completed, providing reliable access for heavy trucks and supporting efficient industrial logistics.
The External Main Road is 75% complete, strengthening connectivity between the zone, the national road network, and Sihanoukville Autonomous Port, while supporting efficient logistics and the growth of heavy industries.
Substation
Construction of the substation is completed. With our substation now operational and directly connected to the national electricity grid, ISI SEZ is ready to deliver large-capacity, stable, and reliable power to our clients
WORKER DORMITORY
The construction progress has now reached 57%. Once completed, the development will provide dedicated accommodation to support the growing workforce within ISI SEZ, further strengthening the zone’s long-term operational capacity and tenant readiness.
FACTORY CONSTRUCTION PROGRESS
The tenant factory has reached full completion and has commenced operations, representing a significant milestone for ISI SEZ. The operational facility reflects the zone’s growing industrial activity and reinforces its position as a ready platform for manufacturing investment.
The second tenant factory is now fully completed and operational, further strengthening production support for the first tenant and enhancing the growing industrial cluster.
Updated on 20 August 2026